Versova STP project: BMC warns of penalty if March 2027 deadline is missed
With around 80 per cent of the project completed, the civic body has directed the contractor to ramp up construction, increase the workforce from 340 to 500 by October 31, 2026, and operate in three shifts to meet the deadline