AG's report: Works Ministry addresses delays, cost increases in Sabah Pan Borneo project

New Straits Times ·
Malaysia

KUALA LUMPUR: Changes in the implementation method, the Covid-19 pandemic, land acquisition and utility relocation issues, as well as contractor performance have contributed to delays in the Phase 1 Sabah Pan Borneo Highway (LPB) project.